Permanent power reaches parts of South Niagara Hospital

Earthworks and construction equipment at the South Niagara Hospital site in 2023.
Foundation work at the South Niagara Hospital site in Niagara Falls in 2023. FILE PHOTO / NIAGARA HEALTH

Permanent power is now available in parts of the South Niagara Hospital, allowing crews to begin testing building systems ahead of the facility’s planned 2028 opening, Niagara Health says.

In a Nov. 17 construction update, the hospital organization said the electrical connection enables commissioning — checking that systems and equipment work as intended before patients arrive.

The milestone applies to selected areas of the building. Construction continues elsewhere, with upper floors at an earlier stage than the lower levels.

Crews are installing flooring, ceilings, cabinetry, doors and other interior finishes on the lower floors, Niagara Health said. A patient bedroom is being mocked up on site to check details before the remaining rooms are completed.

Temporary heating has been switched on throughout the building for the winter. Niagara Health said stable indoor temperatures are needed for interior installation and testing.

Outside, work continues on roads, parking lots, curbs and fencing. Landscaping includes soil preparation and tree planting.

The construction update includes November photographs. Residents can also follow the project through Niagara Health’s construction camera.